Many mistakes in FLC's trillion project
Dozens of projects in 2 projects of FLC Group have been put into use but have not been licensed or have not been accepted for quality.
The Ministry of Construction has just concluded the inspection of two projects in Sam Son (Thanh Hoa) and Nhon Ly (Quy Nhon, Binh Dinh) of FLC Group in the implementation of construction work under the planning , Quality management of construction works and real estate business. The 7-page report shows the violations of Thanh Hoa Province's People's Committee, Binh Dinh Province as well as the owners of these projects.

For the FLC project in Thanh Hoa, the Ministry of Construction inspector said that from 2013, the provincial People's Committee has approved the golf course planning, before the Prime Minister agreed to add to the planning for 11 months.

The People's Committee of Thanh Hoa province also allowed to change the purpose of using more than 11ha of protective forest land to make golf courses violate the regulations of the Prime Minister. This agency also allows the conversion of the purpose of using more than 11ha of protective forest land to implement the Sam Lam FLC project when the conditions for implementing the Law on Forest Protection and Development are not met. The provincial People's Committee of Thanh Hoa province also did not issue a decision approving the 1/500 master plan for golf course and eco-urban project of this investor in Quang Cu.


flc
Resort project of FLC Group in Quy Nhon. Photo: FLC

Department of Construction licensed the construction of two works under the Sam Lam FLC and a project under the Sam Lam FLC when it was completed. There are 2 works under the Sam Lam FLC project and two works under the Sam Lam FLC project. Gofl Links has been completed but the inspection time has not got construction permit.

For the golf resort complex, resorts and resorts in Nhon Ly and Binh Dinh, the inspectorate also said that the provincial People's Committee approved the detailed construction plan at the rate of 1 / 500 does not fit with the 1/2000 blueprint.

Management Board of Binh Dinh Economic Zone authorizes 7 completed works under this project. Five other works have been completed but no construction permits yet.

On behalf of FLC Corporation, the inspection agency said that the owner has many mistakes on the construction planning. Regarding the quality management and works, in both projects, the investor does not have the records of construction survey, or the organization does not meet the standards ...

Many of the projects in the two projects have no records of construction quality management. Especially, at FLC Sam Son, the investor also organized the construction and has been put into use without a license of 7-storey hotel with a total area of ​​over 4,000m2. The 15-storey hotel, with an area of ​​over 75,000m2, the resort and technical infrastructure will also be constructed without a license. Many constructions do not have pre-acceptance test of fire prevention and fighting.

The status of construction without permits, not approved environmental impact assessment, no check acceptance of fire prevention also occurred with a series of projects in Quynhon FLC project.

The consultants, surveyors, supervisors, construction contractors of these two projects are also assessed by the inspectorate as having no license.

The inspectorate suggested the People's Committee of Thanh Hoa province, Binh Dinh to clarify responsibilities to organizations and individuals for the above violations. At the same time, the Inspectorate of the Ministry of Construction also emphasized reporting to the Prime Minister and asking for guidance on the content of the permit to change the purpose of use of protective forest land for golf course purpose, Construction of the FLC.

The inspection agency requests the investor to stop construction, force the quality inspection of the part of the work already completed and complete the legal dossiers on the quality management of the construction works.


For 9 rest resorts, golf courses, commercial areas ... have been completed but have not been licensed to build 2 projects, the inspection agency required to apply for construction permits, quality control , Should be checked by the management agency before acceptance into use. 10 completed and licensed works, the Inspectorate of Ministry of Construction required quality verification and full implementation of legal documents.

The inspectorate said that the provincial People's Committee of Thanh Hoa, Binh Dinh, relevant departments and investors had to report the implementation of the recommendations in September.

Exchanging with VnExpress, the owner said that this unit has received the conclusion of the inspection and is taking corrective measures, complete the procedure. However, he explains that "works that have not been completed for a license are spiritual or small-scale works."

FLC Sam Son and FLC Quy Nhon are two ecotourism tourist groups of FLC Group with hotel, resort and golf courses. The 5-star resort resort of Sam Son FLC has an area of 200ha, total investment 8000 billion. The project includes 5-star facilities and amenities such as 18-hole golf course, international convention center, high-end resort villas, hotels, villas, amusement parks ... This project has been put into operation since 2015.